Queensland’s hospitals are the backbone of the health system, helping our hardworking health workforce to care for more than a million people each year.

When the Capacity Expansion Program (CEP) was announced in 2022, it followed eight years of underinvestment in health infrastructure in Queensland. As our population grew, our hospitals were struggling to keep up with demand. The health system was in crisis.

Infrastructure suffered, needing $2 billion in maintenance and repair alone.

Ambulance ramping was the highest it has ever been, and unprecedented numbers of people were left lingering on surgery wait lists.

Ambulance ramping

This chart shows the percentage of ambulance ramping from 2015 to 2024, with a sharp increase between 2020 and 2021.

Ambulance ramping
Year Year average Jan - March April - June July - September October - December
2015 16.2% 14.8% 14.6% 19.1% 16.4%
2016 19.2% 19.4% 18.7% 19.6% 19.2%
2017 21.5% 21.1% 19.4% 25.4% 20.0%
2018 23.0% 22.3% 20.9% 24.1% 24.6%
2019 27.3% 26.2% 25.1% 31.0% 27.1%
2020 26.6% 26.6% 19.3% 27.6% 32.8%
2021 39.2% 38.3% 40.9% 39.4% 38.3%
2022 43.1% 42.6% 44.9% 43.7% 41.3%
2023 43.5% 42.7% 44.9% 43.3% 43.1%
2024 42.7% 45.5% 44.7% 41.6% 39.1%

Elective surgery waiting lists

Line chart showing a steady rise in the number of people waiting for elective surgery from 2015 to 2024, increasing from around 37,000 to over 63,000.

Elective surgery waiting lists
Year Year average Jan - March April - June July - September October - December
2015 37,022 n.r.* n.r.* 36,427 37,617
2016 41,651 38,202 41,142 42,541 44,720
2017 50,095 47,096 49,369 51,410 52,506
2018 53,411 52,533 52,959 53,582 54,570
2019 54,899 53,793 53,482 56,145 56,176
2020 54,816 55,829 54,137 54,377 54,922
2021 56,834 55,388 56,745 57,343 57,858
2022 58,667 58,895 57,914 58,553 59,307
2023 59,025 58,446 58,362 59,014 60,278
2024 63,066 60,038 61,421 64,171 66,632

The decision to develop the Capacity Expansion Program (CEP) was a hurried attempt to address the state of crisis gripping the health system.

As issues emerged across the CEP, including significant project delays and increased costs, the new Queensland Government announced an independent review in 2024. The Independent Review into the CEP (the Review) found extensive evidence that the planning and execution of the CEP lacked in many critical areas.

Poor planning

  • The CEP was assembled in around six weeks, a process that under regular circumstances would have taken around six months of detailed planning for each project.
  • Business cases were not completed prior to announced budgets.
  • Projects were developed without consulting clinicians and considering local priorities.
  • Critical services were left out of projects due to a lack of consultation and planning.

Low productivity

  • Contractors and subcontractors were required to apply Best Practice Industry Conditions (BPIC) – a major contributor to project cost blowouts and delays.
  • Because of BPIC, Queensland construction sites are less productive than the rest of the country.
  • On just one project, the impact of BPIC is estimated to contribute more than $130 million in additional costs.

Rushed delivery

  • Rushed contracting without proper planning saw projects blow out by 75% within months, requiring an additional $1 billion.
  • The plan unrealistically attempted to deliver all major projects in a single stage.

Delays

The Review found that every project in the CEP was underfunded, delayed, did not deliver on critical service needs and was ultimately undeliverable. In some cases, projects had doubled in cost and were delayed from anywhere between six months to more than three years. Without major intervention, none of the projects were able to be delivered in their current form.

Cost blowouts

Because of poor planning, low productivity, rushed delivery, and delays, costs blew out by approximately $7 billion.

Project Announced budget Actual or forecast costBlowout
The Prince Charles Hospital Expansion $300 million $788 million $488 million
New Queensland Cancer Centre $750 million $1.8 billion $1.05 billion
Redcliffe Hospital Expansion $1.06 billion $2.122 billion $1.062 billion
New Toowoomba Hospital $1.3 billion $1.98 billion $680 million
New Coomera Hospital $1.3 billion $2.254 billion $954 million
Mackay Hospital Expansion $250 million $520 million $270 million
Townsville University Hospital Expansion $530 million $1.029 billion $499 million
New Bundaberg Hospital $1.2 billion $2.306 billion $1.106 billion
Cairns Hospital Expansion $250 million $628 million $378 million
Hervey Bay Hospital Expansion $40 million $94 million $54 million
Logan Hospital Expansion $530 million $875 million $345 million
Ipswich Hospital Expansion $710 million $925 million $215 million
QEII Hospital Expansion $465 million $621 million $156 million
Princess Alexandra Hospital Expansion $350 million $761 million $411 million